Duration of Storage

3 storage years (1. 4. 2026 - 31. 3. 2029)

Working Gas Volume

500 000 MWh

Injection Output

6 370 MWh/day

Withdrawal Output

8 860 MWh/day

Size of Additional Capacity

300 %

25.7.2025 | (473x)

Storage Capacity Auction 29 July 2025

Auction Date: 29 July 2025, 10:00 a.m. (CEST)

Type of storage capacity reserved: Monthly storage capacity with the interruptible output

Working Gas Volume: 55,000 MWh

Interruptible Injection Output (flat): 1,800 MWh/day (31 days)

Interruptible Withdrawal Output (flat): 1,100 MWh/day (62 days according to curve)

Duration of Storage: 8 storage months (1 August 2025, 6 a.m. - 1 April 2026, 6 a.m.)

 

For additional information please contact: auction@mnd-es.cz
Ing. Josef Brůček Tel.: +420 775 877 182
Filip Červenka Tel.: +420 775 875 092

Sample Storage Contract